Promon/Odebrecht - UTE Três Lagoas GT 1 - 2 - 3 - 4
Isolated Phase Bus 

13,8kV - 5000A
 

TRÊS LAGOAS Power Project consists of the implementation of the a combined-cycle gas fired power plant in TRÊS LAGOAS,MS State in the border with S.Paulo State and was built by Consórcio PROMON/ODEBRECHT in a turn key basis for PETROBRÁS, Brazil, owner and 100% investor of the project. 
 
The first stage of the plant consists in 04 combustion turbines  60MW GE/ALSTOM in operation since 2003 in open cycle and more 02 steam turbines that when added will allow  UTE TRÊS LAGOAS to operate in combined cycle 4x2 producing 360MW 
 
For this project,due short and fast track delivery required in order quick start plant operation because of energy crisis in Brazil in 2001/2002 the Isolated Phase Bus were designed in Brazil by Powerbus and manufactured in Calvert Company factory in Jackson,USA. 
 
Powerbus also performed contract management in Brazil and renderedd all site services  for this project,including welding and erection supervision of IPB's and aluminum welding of bus conductors and connectors for double busbar AIS 138kV Substation connecting the plant to National Interconnected Grid and CTEEP power system.  
 
Powerbus also supplied for this project 02 special designed Interrupting Switchgear 15kV-1250A and short circuit rated 65/170kA associated with IPB's for feeding all ancillary BOP services of the plant
.

 

 

 
©2004 Powerbus., all rights reserved.